ISTQB 연습문제 풀이 - Exam D : Q#6

Test Management Role Responsibilities

1. Introduction

In the ISTQB Foundation Level syllabus, testing responsibilities are divided between the testing role and the test management role.

Understanding this distinction is essential for answering role-based exam questions.

ISTQB Foundation Level에서는 테스팅 역할(Testing role)테스트 관리 역할(Test management role)의 책임을 구분합니다.

이 문제는 어떤 작업이 테스트 관리자의 역할에 해당하는지를 묻습니다.


2. Practice Question

❓ Question

Which of the following is MOST likely to describe a task performed by someone in a test management role?

  • a) Evaluate the test basis and the test object
  • b) Define test environment requirements
  • c) Assess testability of the test object
  • d) Create the test completion report

✅ Correct Answer: d)


3. Explanation

✔ d) Create the test completion report — Correct

The test management role focuses on:

  • Test planning
  • Test monitoring and control
  • Test completion activities

Creating the test completion report is a key output of the test completion activity and is therefore typically performed by test management.

테스트 관리 역할은 테스트 계획, 모니터링·통제, 테스트 완료 활동을 담당합니다.

테스트 완료 보고서(Test completion report)는 테스트 완료 단계의 핵심 산출물이므로 테스트 관리자가 수행하는 작업입니다.


❌ a) Evaluate the test basis and the test object — Incorrect

Evaluating the test basis and the test object is part of test analysis.

Test analysis is a technical activity typically performed by the testing role.

테스트 베이시스와 테스트 대상 평가 작업은 테스트 분석(Test analysis)에 해당하며 테스팅 역할의 책임입니다.


❌ b) Define test environment requirements — Incorrect

Defining test environment requirements is performed during test design.

This is a technical preparation task, not a management activity.

테스트 환경 요구사항 정의는 테스트 설계(Test design) 단계의 작업으로 관리 역할이 아닌 테스팅 역할의 책임입니다.


❌ c) Assess testability of the test object — Incorrect

Assessing testability is also part of test analysis.

It helps determine how easily the system can be tested, which is a technical concern.

테스트 가능성(Testability) 평가는 테스트 분석 단계에서 수행되는 기술적 활동입니다.


4. Summary Table

Option Activity Area Test Management Role? 요약
a Test analysis ✖ No 테스팅 역할
b Test design ✖ No 설계 활동
c Test analysis ✖ No 기술 활동
d Test completion ✔ Yes 관리 역할

5. Final Takeaway

For the ISTQB exam, remember this distinction:

Testing role = technical testing activities
Test management role = planning, monitoring, control, and completion

시험 대비 핵심 정리입니다.

테스팅 역할 = 분석·설계·구현·실행
테스트 관리 역할 = 계획·모니터링·통제·완료

Related: More ISTQB Posts | Next Question

다음 이전